Frustration, anger continue to mount over Highway 101 work

SOLANA BEACH ā€” When the city broke ground in June on a project to improve Coast Highway 101, the owner of the construction company selected for the job said he only makes promises he can keep.Ā 

ā€œAnd I promise there will be times when you wish I wasnā€™t here, like when construction begins,ā€ said Glen Bullock of Dick Miller Inc.

ā€œBut Iā€™ll try to minimize the frustration and I promise youā€™re going to love me when I leave,ā€ he said.

It will be at least six to nine months before the project is complete and the latter statement can be confirmed, but Bullock couldnā€™t have been more accurate with the first part of his pledge.

Frustration has turned to anger and fear as business owners deal with lost revenue, especially during peak holiday shopping time, and the reality that some may not be able to survive until the project is finished.

Lawsuits and restraining orders have been threatened. A safety inspection was requested.

Sue Kelly, who owns Fairbanks Interiors and Something Madd Boutique, said sales are down about $2,000 a month since construction started.

ā€œMost of our business is from people driving by,ā€ said Christine Tolentino, who works with Kelly. ā€œNo one is stopping anymore. No one wants to drive through dirt. They canā€™t see the driveway and thereā€™s nowhere to park.ā€

Rosemarie Houston said sales are down 25 percent at her store, Bon Bon Furniture and Accessories.

ā€œIā€™m dying over here,ā€ said Lauren McChrie, owner of Oskadusa Bead Shop, which has been at its Highway 101 location for 21 years.

ā€œIā€™ve seen it bad, even in 2007 when the economy was down,ā€ she said. ā€œBut Iā€™ve never seen it like this. Iā€™m a destination store and people canā€™t get to me.ā€

Station Sushi, a 12-year city mainstay thatā€™s normally packed for lunch, served three tables on a recent Monday, owner Chung Choi said.

Bartenders at Pizza Port have had to take on second jobs, the manager there said, and John Lind, who owns a home furnishings store, said he had $58 in sales during a recent 10-day stretch.

Merchants have also complained about rude and disrespectful workers, a sloppy jobsite, safety concerns and traffic problems.

Store owners voiced these and other concerns during a Dec. 10 meeting with Bullock, the city engineer and the cityā€™s project manager.

Bullock, a retired Marine, said as a small-business owner, he sympathizes with the merchants.

ā€œI feel your frustration,ā€ he said. ā€œTell me what I can do to help you.ā€

For starters, merchants suggested better signage and lighting.

Bullock said he canā€™t go back and fix what has already happened but he wants to meet with business owners on a regular basis to hear recommendations on how to make things better going forward.

ā€œI will commit myself to make this work,ā€ Bullock said.

By the end of the meeting most of the anger was refocused on city officials.

Business owners said theyā€™ve shared their concerns with city staff but nothing seems to get done.

ā€œWe need your help,ā€ Houston said to City Engineer Mo Sammak. ā€œWe donā€™t get your support. All we hear is that youā€™re ahead of schedule. To me thatā€™s a slap in the face. Every day Iā€™m struggling.ā€

Sammak said their concerns havenā€™t fallen on deaf ears. He said night work was added Dec. 10 to Dec. 12 and an electronic sign that will allow changeable messages to direct customers is being purchased.

City Manager David Ott said several people approached him at a recent event and ā€œrecognized the city was working hard on the project and trying to minimize the impacts.ā€

At 3:40 on a recent Monday afternoon, most businesses along the construction corridor were essentially void of customers, while to the north, along Coast Highway 101 in Encinitas, business was booming.

ā€œThatā€™s what weā€™re trying to create,ā€ Councilwoman Lesa Heebner said, recalling that when improvements were made in Encinitas, merchants in that city had the same concerns.

ā€œI wanted assurances that wouldnā€™t happen here,ā€ she said. ā€œIā€™m sympathetic. Weā€™re doing as much as we can financially do. But we can always do a better job with communications.ā€

Council members were inadvertently not notified of the Dec. 10 meeting, but Heebner said she would be ā€œmore than happyā€ to attend future meetings with Bullock and business owners ā€œto find solutions.ā€

The $7 million project will improve the highway from Cliff Street to Dahlia Drive. It will feature gathering places, new crosswalks, additional parking and a shared bike lane. Originally slated to take 15 months, the project is about three months ahead of schedule.