Crews prepare for San Onofre dome demolition

REGION — Demolition crews are expected to begin tearing down the twin domes at the San Onofre Nuclear Generating Station in 2027, removing a familiar landmark along Interstate 5.

The nuclear power plant opened in 1968 on the coast west of I-5, just north of Camp Pendleton and south of San Clemente. It provided carbon-free electricity to the region before Units 2 and 3, housed in the twin domes, went offline in 2012.

About 1,600 metric tons of spent nuclear fuel remain on-site in steel canisters housed in concrete vaults. The fuel will remain there until the federal government finds a location to move it.

At a Nov. 5 meeting of the plant’s Community Engagement Panel, Joe Nowak, executive sponsor for general contractor San Onofre Decommissioning Solutions, said the project was about 90% complete and interior demolition of Unit 3 was underway.

Crews are expected to begin exterior demolition of both units in 2027 and finish dismantling them in 2028.

Nowak also discussed two unintended wastewater releases. On Sept. 23, about 5,000 gallons of wastewater from demolition work entered Unit 2’s storm drain system and discharged offshore. On Nov. 3, a hose failed, spilling 900 gallons of wastewater onto asphalt.

In both incidents, pH levels exceeded permit limits, prompting notifications to the San Diego Water Quality Control Board.

Nowak said crews will treat and release about 1 million gallons of water after a recent breach in a basement wall below the water table. Crews will release the groundwater in batches after adjusting the pH and ensuring that levels of suspended solids meet regulatory limits.